Let’s energize the Aderis CommsSafe for the first time, and walk through the commissioning process to ensure everything is working properly.


Safety First!

This procedure is written to follow the conditions set by the prior section of this manual, Pre-Energization Checks.

If you have not yet performed the Pre-Energization Checks, or have taken any actions that altered the as-left conditions of the Aderis CommsSafe set forth at the completion of the Pre-Energization Checks, we strongly recommend performing the Pre-Energization Checks before proceeding.


The following steps will require authorized and qualified commission staff to energize the Aderis CommsSafe. Appropriate personal protective equipment (PPE), electrically rated tools, and knowledge of the energization process are required perform the energization process.

Improper PPE, tools, and/or knowledge may result in staff being exposed to branch circuit and electric shock could result in injury and/or death.

The following steps should only be conducted by authorized and qualified commission staff.


Everything in box is 120VAC or 24VDC

Utilize this wire key:

Screen Shot 2022-05-16 at 1.29.53 PM.png

Controls Energization

Energizing the Control Panel will also energize the Meter and Protective Relay, enabling addition commissioning verifications.

Addition Commissioning Verifications:

  1. Proper Battery UPS Energization
  2. Networking & SCADA Equipment Energization